Drakes et Al v Plantation Beach St. Lucia Ltd

JurisdictionSt Lucia
CourtHigh Court (Saint Lucia)
JudgeBelle, J.
Judgment Date15 January 2015
Neutral CitationLC 2015 HC 1
Docket NumberSLUHCV2008/0659
Date15 January 2015
Drakes et al
and
Plantation Beach St. Lucia Ltd

Belle, J.

SLUHCV2008/0659

High Court

Contract Law - Construction contract — Partially oral and partially written contract — Whether the contract sum was actually for the amount claimed by the claimant — Whether the claimants delivered materials costing the amount they claimed — Whether the claimant undertook additional works valued at the amount claimed — Whether the defendants were entitled to the return of part of the money paid to the claimants on the basis that there had been an overpayment.

Appearances:

Mr. Colin Foster for the claimants.

Ms. Diana Thomas and Ms. Renee St. Rose for the defendant.

Belle, J.
1

Article 945 of the Civil Code states:

“When the meaning of any part of a contract is doubtful, its interpretation is to be sought rather through the common intent of the parties than from a literal construction of the words.”

2

Article 946 of the Civil Code states:

When a clause is susceptible of two meanings, it must be interpreted as that which would have effect and not of that which would have none.”

3

Article 947 of the Civil Code states:

“Expressions susceptible of two meanings must be taken in the sense which agrees best with the context.”

4

A construction contract has many component parts which create obligations between builder and owner and those responsible for the many aspects of the building works. In a case such as this where the central purpose was the completion of a number of units of a resort complex it is at the core of the matter and the burden lies with the claimant to prove that it had adhered to the contract terms and completed such work as was required and was reasonably possible in the circumstances.

5

The defendant, would bear the evidential burden to rebut allegations of the claimant intending to show that the contract has been breached and that the claimant did not interpret the contract reasonably and in keeping with its context.

THE CLAIM
6

I agree with the approach taken by the defendant in describing the claimant's claim as follows: The claimant's claim is for:

1
    The sum allegedly due and owing and unpaid on a contract for the sum of $806,080.00 2. The sum allegedly due and owing for the purchase of sundry items plus charges and interest on the goods purchased at the rate of 35% being $163,297.44 and $57,154.10 3. The sum allegedly due and owing for extra remedial works completed plus supervisor's fee of 15% being $165,907.56 and $24,886.13 respectively. The total amount is $190,793.69 4. The total claim is for $1,217,325.00 less $688,000.00 admitted to have been received by the claimant from the defendant. The claimants therefore claim that a balance of $529,325.00 is due and owing to them
5

The defendant has defended the claim on the following grounds:

1
    The contract between the claimants and the defendant was for $698,310.00 inclusive of Builder's Work ($597,000.00) and Mechanical, Electrical and Plumbing Work ($101,310.00) 2. The claimant only delivered materials valued at $147,453.23 and that an amount of 12.5% was payable for overheads and profit amounting to $165,884.88. 3. That the claimants only claimed a sum for additional works of $30,139.34 but that the value of the additional work amounted to $10,396.75. No additional claims were made and assessed. 4. The defendant also filed a counterclaim on the basis that the work done within the contract, the materials delivered, and the additional work done, the defendant had overpaid the claimants by $208,071.5. The defendant claimed that it also paid other persons an additional $44,476.67 to make good the claimants' poor workmanship and to mitigate its losses. Special damages of $252,548.42 were claimed.
6

I also agree with the defendant's counsel that the claimant would be required to prove the following:

  • (i) The contract sum was in fact for $806,080.00

  • (ii) The claimants delivered materials costing $163,297.44 to the defendant.

  • (iii) The defendant agreed to pay the claimants a commission of 35% on top of the cost of material deliveries;

  • (iv) The claimants undertook additional works valued at $165,907.56;

  • (v) The defendant agreed to pay the claimants a supervisors fee of 15% of the value of the work done; and

  • (vi) There were facts to support a claim for aggravated and /or exemplary damages.

WAS THE CONTRACT SUM IN FACT FOR $806,080.00?
7

The claimants state that there was a contract which was both written and oral. According to the claimant this contract was created during meetings between the parties along with several discussions and conversations between Michael Pilgrim, Garvin French and Martin Matthews and the claimant.

8

The defendant claims that the only evidence of a written agreement between the parties was an undated document bearing the signature of Ian Harrison, Project Quantity Surveyor for the defendant and Benjamin Drakes and Gerald Francis on Behalf of the claimants. The defendant points to a schedule to the document No 15 under the head “Contract Rates” which is found at Trial Bundle 324. This document shows the total contract sum to be $698,310.00.

9

The defendant also refers to another document at page TB328 where another version of document 15 is exhibited labelled as document 16 which contains the same details as document 15 except that it is endorsed with the words “N.B. Not as per the original agreement” along with what appears to be the signature of Benjamin Drakes.

10

Counsel for the defendant argues that the claimant appears to be using the two documents to suggest that Documents 15 was not the written contract between the parties. No allegation was made neither was any evidence led to the effect that any person representing the defendant agreed to accept Mr. Drakes endorsement made after he had signed the agreement, counsel argues.

11

It is important that specific aspects of this much scrutinized document be examined at this point. The document is Titled “Subcontract Agreement” and the parties to the said agreement are Plantation Beach (Saint Lucia) Ltd. the defendant and TECC, the third claimant. The Description of the works is General Building Works.

12

The parties have disagreed as to whether this document forms the substance of the contract. The claimant says it does not and that it is a modification of what was agreed yet the representative of the claimants signed the Document. He explained however that this document was required to access funds from the company's bankers and was signed under pressure.

13

Some of the pivotal clauses in the document include:

  • “2. Subcontractor shall provide sufficient labour to execute the works programme.

  • 3. Subcontract commencement —26 March 2007

  • 4 Duration of subcontract —3 months

  • 5. Completion date-26 June 2007

  • 9. There shall be no Retention withheld

  • 10. Payments will be made 7 days from the receipt on each monthly valuation submitted by the Subcontractor.

  • 11. Subcontract rates are fixed,

  • 12. Subcontract sum is EC$698,310.00 as per the attached schedule of Rates.

  • 13. Subcontract is not subject to remeasure, however if buildings are deleted from your scope of works then the contract sum shall be adjusted using the rates as per the schedule.

  • 14 Subcontractor shall have an experienced supervisor on sight at all times.

  • 15. Main Contractor shall ensure that sufficient areas are available to progress the Subcontract works.

  • 16. Subcontractor is responsible for making good all defective works.

  • 18. Main Contractor shall free issue specialist finishing items, namely, but not limited to, sanitary ware, faucets and the like, tiles, kitchen surfaces and work tops etc.

  • 19. Subcontractor shall supply all other “locally available” materials namely but not limited to, paint, salient, stains, fixings, cornice, skirting, sundry timber, tile gout, thinset, drywall, compound and the like. All said materials shall be delivered to and registered in to the Main Contractor stores and then reissued to for use in the works by the Main Contractor's staff. The cost of the said materials shall be reimbursed to the Subcontractor within his monthly valuation payments.”

14

The document was signed by Ian Harrison, Project Quantity Surveyor for the defendant and Benjamin Drakes for the claimants. It is evident that many of the issues central to the arguments between the parties are referred to in the agreement while others are not. Indeed this is indicative of the weak framework of the working agreement between the parties.

15

The court has formed the impression that there was a very poor contractual framework supporting whatever agreement existed between the parties. Consequently we are left with a totally unsatisfactory situation in which the court is being asked to determine the rights of the parties based on conversations and discussions.

16

From the very outset the defendants were unable to pin down the terms of the contract when they pleaded in their amended Defence:

“The defendant denies paragraph 7 of the Statement of Claim and states that the whole of the agreement between the parties as it relates to the retrofitting of buildings was made in writing and contained in the Agreement referenced PBL/01/TECC. This said contract was varied orally where the defendant agreed to an extension of time after the 26 June 2007 deadline. The defendant further states in respect of additional remedial work that it was not given an opportunity to negotiate said work with the claimants but that the claimants carried them out in any event.”

17

The defendant further repeats that the whole of the contract was contained in the Agreement referenced PH/O11 TECC except as it relates to variations which were discussed after the contract was commenced. As further regards paragraph 9 of the Statement of Claim, the defendant states that the endorsement made on the contract by Benjamin Drakes...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex

Unlock full access with a free 7-day trial

Transform your legal research with vLex

  • Complete access to the largest collection of common law case law on one platform

  • Generate AI case summaries that instantly highlight key legal issues

  • Advanced search capabilities with precise filtering and sorting options

  • Comprehensive legal content with documents across 100+ jurisdictions

  • Trusted by 2 million professionals including top global firms

  • Access AI-Powered Research with Vincent AI: Natural language queries with verified citations

vLex